Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Getting overall progress in P3

3 replies [Last post]
Frank Duncan
User offline. Last seen 19 years 39 weeks ago. Offline
Joined: 25 Oct 2005
Posts: 6
Hi, I have some questions for the experienced P3 users.

First, I wish to know about the % COMP field (PERCENT COMPLETE) on a resource-loaded schedule for a construction project. The % COMP is based on what?

- Quantities installed?
- Duration consumed?

Second, knowing that this % COMP field is valid only for each activity, how do you get the overall progress? I wish to get the S-curve graph with the planned and actual lines, but how do you get it if the activities have different unit of measures (i.e. LM, M3, EA, and so on)? If you use a unified unit of measure, what report do you use and what data do you export to elaborate the graph using thrid party software, such as Excel (they told me P3 is bad elaborating graphics)?

Thank you very much.

Replies

Raja Izat Raja Ib...
User offline. Last seen 14 years 10 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Hi Frank,
Try go to "View>Resource_profile" for screenshot, u also can print it. On second thought by using report writer u can create your own reporting summary.
Jackie Gilliland
User offline. Last seen 15 years 6 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 41
Groups: None
In P3 be carefull of using activity summarization for determining % complete.

I suggest you use a Resource Control Summary report from Tools/Tabular Reports/Resource/Control. Make a selection for the same group of activities you would like to summarize.

I suggest you run this report and compare the numbers to numbers from a summary bar to check for correctness.

Jackie
Brennan Westworth
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
In P3 go to Tools>Options>Summarization...

There you can select how you want P3 to summarise the % complete for your activities.

You can choose from duration, resource units or cost.

With a fully resource loaded schedule I recomend resource units for construction progress and cost for overall design, procurement and construction progress.

Enter your % complete at an activity level acording to physical progress. Physical progress is not simply a units completed / total units calculation. For example you may be building a simple building consisting of 4 brick walls. Bricking up the corners takes considerably more time than the in-fill brickwork. Another example is structural steel erection, by just using a quantity method (eg tonnes of steel) erecting one large column will earn you a disproportional amount of progress compared to the infill steel. Factors like this need to be considered when defining your activity breakdown and progress.

Reports can be generated in P3 using the resource/cost profile.