Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to progress-Piping Instalation

5 replies [Last post]
Carmen Arape
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292
Piping Instalation-Large Bore & Small Bore- Progress measurement

Progressing the activity instalation, I have the following question:

Milestones were defined to progress the work. For each Milestone I need a quantitiy estimate to track the progress as follow: executed quantities/total estimate. My question is: what type of estimate I should have for each milestone such as:
Erect&fit up: Equivalent linear meter (straight lines+spools) / total equivalent linear meters.
Welding : welded inches / total inches.
Pipe suport : units of supports / toatl supports to be installed.
Test : No idea
Valve install.: installed valves / total valves

Appreciate any HELP
Thanks
Carmen (working at Construction SITE in Venezuela)

Replies

Raj Maurya
User offline. Last seen 4 years 1 week ago. Offline
Joined: 17 Jul 2004
Posts: 132
Carmen,
As you said you are controlling LSTK EPC, you no need to monitor the progress on MH instead I suggest you to use inch-Dia for fit and inch-meter for erection and same for hydrotesting.
Carmen Arape
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292
Hi Andrew

When you mention meters by sections,it looks like easy for straight sections, but how do I do with spools ? Should I include them or not?.

Thanks, Carmen
Carmen Arape
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292
Hi Jaco

My E-mail is cararape@cantv.net and I would like the book that you mentioned. I am controlling an EPC lump sum contract and the contractor is using man-hours for weighting the lines by AREA and quantity estimates for each progress milestone.

Lot of Thanks
Andrew Podolny
User offline. Last seen 1 year 52 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 130
Hi carmen
We’re using meters as unit of measure for hydraulic testing of pipeline. Testing is performed by sections (i.e. from one block valve to another). Usually it takes some time to fill the pipeline by water and to gain the testing pressure (depending of the length of the section and DN) plus 24 hours for retention.
When testing particular assembly unit (ball valve for instance) the right unit of measure is psc.
Hope it’ll help.
Best regards,
Andrew
Jaco Stadler
User offline. Last seen 18 years 38 weeks ago. Offline
Joined: 9 Sep 2004
Posts: 299
Groups: None
Hi Carmen send me our email addres (need to send 2 x 5 meg file) this is a book that wil help you I would suggest manhurs

Jaco Stadler

(jaco.stadler@snclavalin.comO