P3 set up enquiry

1 reply [Last post]
Colin Stirling
User offline. Last seen 12 years 9 hours ago. Offline
Joined: 7 Sep 2003
Posts: 5
Groups: None
Schedule details

P3 schedule containing up to 500 logically linked and/or constrained activities, with an hourly planning unit and a calendar based on an 8 hour shift.

Problem

When project is levelled (and scheduled), I want the software to automatically delay an activity, if it cannot start and finish in the same shift. (i.e. only 1 hour of shift available and activity is 2 hours
duration, therefore delay until next shift.)

Can anyone suggest how to set up P3 to undertake the above.

Replies

MK TSE
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
In Tools - Level - splitting, set the maximum number of splits per activity is 0
i.e. no split allowed.