Resources Assignment

1 reply [Last post]
Usman Yasin
User offline. Last seen 3 years 12 weeks ago. Offline
Joined: 27 Mar 2020
Posts: 4
Groups: None
I am trying to assign resources to the activities but every time i do that, budgeted unit changes automatically. I checked my calendar, it is set on the exact requirement, but still the same issue.

Can anyone help?

Replies

Zoltan Palffy
User offline. Last seen 3 days 5 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

make sure that you duration type is fixed duration and units/time add a column and do the 1st one and then do a fill down

next go to Projectsand in the Default tab make sure that you duration type is fixed duration and units/time