Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

change order and reflection in baseline

2 replies [Last post]
Ahmet Tuter
User offline. Last seen 4 years 16 weeks ago. Offline
Joined: 7 Feb 2013
Posts: 52
Groups: None

All change order modify the baseline in some way, such as cost, scope or time. but we do not create a new baseline everytime.

how do we reflect this change order which only modifies part of the basline, in the baseline?

for example, lets say we are building a house, and a change order added a 10 meter wall. we add an activity or activities for building that wall, put in its durations resources, money into it ... and when we do earned value calculations, how does it work for this, for something that did not exist before? This is my question I guess

Replies

Zoltan Palffy
User offline. Last seen 10 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

you don't once you have the baseline YOU DO NOT MODIFY THE BASELINE. What you do is you copy the baseline and as the project progresees you PROGRESS THAT schedule this is the updated schedule. Thne can ADD any change orders to the updated schedule then you can compare it to the baseline so that you can see what was added and look for differences. If you add it to the baseline then you will NEVER see any differences. 

Indra Pandu Prasetyo
User offline. Last seen 7 years 4 weeks ago. Offline
Joined: 27 May 2016
Posts: 2
Groups: None

Hi Ahmet,

How often change order occurs? How big is the change order impact to overall schedule?

Yes I agree, we cannot change the baseline everytime. As I understand, baseline contains not only scope, schedule and cost, but also reflect the strategy how to manage the project execution.
Changing the baseline --> change of execution strategy

Based on my experience, if the change order has significant effect to the schedule (ex: shifting overall schedule completion/ key milestone, changing of sequence, changing execution plan, etc.), then re-baseline must be done, and progress plan will follow.
But if it has only small impact to the schedule, no need to do re-baseline, just add new activities to cover change order.

Schedule change history should be made and updated each time change happens in schedule, it will help tracking the schedule in later time.

Indra