Pre-Engineered Metal Building Scheudle

1 reply [Last post]
Najeebullah Safi
User offline. Last seen 2 years 35 weeks ago. Offline
Joined: 20 Jun 2017
Posts: 3
Groups: None

Hello Dear Colleagues, 

 

I am working on a new project which is a big stadium PEB building. I am looking for a sample schedule related to such a building. If anyone has any please send it to via najeebullah.s@yahoo.com 

 

thank you all

Replies

MK TSE
User offline. Last seen 3 years 46 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None

Seem no sample and/or template for stadium PEB building since construction method depend on design and constraints