Acumen FUSE

2 replies [Last post]
Mohammed Shafiq
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 13 Feb 2007
Posts: 13
Groups: None

Hi, 

I need help in understanding how to upload a primavera xer file into FUSE for the DCMA14 check with an attached baseline. The problem I am getting is, FUSE is showing baseline dates which are totally different to my attached baseline dates in the xer schedule. 
I have assigned the baseline to both current project and also the same baseline to the primary baseline but FUSE refuses to pick these dates. 

Any help will be appreciated. 

Thanks

Replies

Thomas Nicholson
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 4 Oct 2006
Posts: 87
Groups: None

I believe you may have to detach the baseline and then import directly into FUSE using the snapshot system.  It's what I do to check for changes from one to the other.  I assume you are exporting the P6 project and if i recall correctly P6 doesn't export the baseline with it or hasn't in the past.

Hope that helps.

 

Thom

Thomas Nicholson
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 4 Oct 2006
Posts: 87
Groups: None

I believe you may have to detach the baseline and then import directly into FUSE using the snapshot system.  It's what I do to check for changes from one to the other.  I assume you are exporting the P6 project and if i recall correctly P6 doesn't export the baseline with it or hasn't in the past.

Hope that helps.

 

Thom