Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Incorporating approved change into the Performance Measurement Baseline (PMB) using P6v7

No replies
steven williams
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 16 May 2005
Posts: 19

I have used the 'maintain Baselines' function to update a copy of the project contract baseline in order to demonstrate slippage in the current schedule when introducing an approved change.

this has not resulted in the transfer of the 'coded up & filtered' activities being copied into the PMB from the current schedule as i had expected. therefore i can't show the slippage using this process.

can anyone suggest an alternative method ??

i have now unlinked the copied PMB from the current schedule and restored it in order to try another process.

thanks