Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

PERFORMANCE PERCENT COMPLETE ENCOUNTER PROBLEM

No replies
manalao salacop
User offline. Last seen 12 years 31 weeks ago. Offline
Joined: 23 Nov 2010
Posts: 4
Groups: None

To all co-Planners,

I have an unexpeted encounter probs:

Facts:

I am using P6.1 stand alone.

Resource loaded and cost loaded (manpower in 0 price/unit and cost in lump sum 1 price/unit).

Using the project as base line.

Duration type: Fixed duration and units

Complete % type: Duration

Problem: 

When i update, activity with 100% complete will give the earned value as 100%.. But for activity with less 100% complete will give any no performance% complete which means that there is no earned value.

Hope that you can give me hands on this one.. thanks..