Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

PHYSICAL PROGRESS

1 reply [Last post]
Vishnu Kant Mishra
User offline. Last seen 13 years 9 weeks ago. Offline
Joined: 14 Feb 2009
Posts: 34
Groups: None
as per my client’s demand i was finding difficulty to show physical progress in p6.it is showing as per 2 activitywise but when i want 2 see d summary then it was not displaying as total in activity wbs summary. so how can i reflect it as %ge.

Replies

Rodel Marasigan
User offline. Last seen 48 min 6 sec ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Vishnu,
All Activity Percent Type (Physical, Duration & Unit) are represented by Activity % complete and Performance % Complete. Use Performance % complete as it has summary but if your program is not cost loaded your summary band will be zero.