Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Scheduling strategy

9 replies [Last post]
Aidan Eagers
User offline. Last seen 17 years 25 weeks ago. Offline
Joined: 16 Apr 2007
Posts: 10
Groups: None
Hi,

I am working on a Pharma project and there are a lot of WBS that are not really related so the project cannot really be linked as one project with one completion float.
Is it reasonable to monitor float on one activity at the end of each WBS, that way any movement in the project can be seen. I know this is not the usual practice but management want to see a schedule, now, now, now but without enough of the information being provided to produce the right structure.

Thanks for any comments

Replies

Stephen Devaux
User offline. Last seen 8 weeks 1 day ago. Offline
Joined: 23 Mar 2005
Posts: 668
Aidan,

In work I’ve done for Drug Information Association, the cost of delay in bringing an average pharma product to market is estimated at about $32. Per second. About $4.6 million per week. I don’t know how much it is for your particular product (if it’s the next Lipitor, add a couple of zeroes!), but you should find out.

If you input constraining dates, it is crucial to quantify their CLUBs (Cost of Leveling with Unresolved Bottlenecks), i.e., how much these constraints are costing by delaying the CPM critical path and project completion. This may allow you to:

1. Justify decisions that would ameliorate the constraints.
2. Look awfully good by showing how many millions of extra dollars your planning and decision-making is adding to the project profit.

Good luck.
Aidan Eagers
User offline. Last seen 17 years 25 weeks ago. Offline
Joined: 16 Apr 2007
Posts: 10
Groups: None
I agree, we have a design team who are shooting specs at the procurement guy without much thought for a plan so even if the schedule was built the idealistic way i would end up constraining dates anyway.
Anoon Iimos
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Aidan,

IMO, there’s no other way but to follow your constrained procurement dates, this is out of your control and you can never nail down the completion dates of each of your WBS if these procurement dates were not defined.
Aidan Eagers
User offline. Last seen 17 years 25 weeks ago. Offline
Joined: 16 Apr 2007
Posts: 10
Groups: None
Thanks Karim, appreciate your opinion
Karim Mounir
User offline. Last seen 10 years 50 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Aidan,

It’s the normal way to drive the procurement dates back from the finish date but actually during updates and the project’s life cycle these originated dates are always delayed many times in the project.
So i didn’t face this except maybe if we are dealing with a subcontractor scope (eg. elevators).

and btw it’s KARIM not KAMIR.

Regards,
Karim

Aidan Eagers
User offline. Last seen 17 years 25 weeks ago. Offline
Joined: 16 Apr 2007
Posts: 10
Groups: None
I wish they would, i get a lot of headaches.

Cold up there?
Anoon Iimos
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
you know the problem with pharma.. projects is the chemistry behind it. So you have to be careful with the WBS as you might label viagra with panadol!
Aidan Eagers
User offline. Last seen 17 years 25 weeks ago. Offline
Joined: 16 Apr 2007
Posts: 10
Groups: None
Kamir,

In this case the WBS that i am treating as seperate are for a procurement cycle, for the instrumentation (small parts but still essential). I have each WBS linked to a milestone so that we get the instrumentation on time but they are not linked in a perfect consecutive order.

Have you come across many schedules that are drivin forward from constrained procurement dates? I know it is better to drive back from finish date required but our validation strategy has not been nailed down and this makes that difficult.

Aidan
Karim Mounir
User offline. Last seen 10 years 50 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi Aidan,

Yes in some projects u can do this, eg. in a cement project the plant consists of departments which are not related to each other (in civil scope) and each department contains more than 1 building, so u link each building within its department and each department should be linked to the completion milestone independently.

HTH.

Regards,
Karim