If the only reason for rebaselining in-progress is due to rate changes, then I do it...it takes a bit to check that the software has actually calculated things correctly though. I like to take a copy of the baseline and muck around with that one first, to make sure things will go smoothly.
Any other time, rebaselining in-progress is a bit of a no-no in my book, particularly in defence environment. So standard thing is to set BCWS = BCWP and replan the remainder...or set BCWS = BCWP = ACWP for a formal reprogramme.
Regards
Joanne
Member for
20 years 4 months
Member for20 years5 months
Submitted by Raja Izat Raja… on Wed, 2005-09-14 03:12
as far i know If re-baseline the progress its does not impact the cost, its only have to shift remaining progress followed by the cost /resource, Unless there is additional activities to be add or labour rate changes (but not very frequent happened) cause there is contract to be followed.
Member for
21 years 9 monthsRE: Re-baselining W.I.P. Activities
Hi Rob
If the only reason for rebaselining in-progress is due to rate changes, then I do it...it takes a bit to check that the software has actually calculated things correctly though. I like to take a copy of the baseline and muck around with that one first, to make sure things will go smoothly.
Any other time, rebaselining in-progress is a bit of a no-no in my book, particularly in defence environment. So standard thing is to set BCWS = BCWP and replan the remainder...or set BCWS = BCWP = ACWP for a formal reprogramme.
Regards
Joanne
Member for
20 years 4 monthsRE: Re-baselining W.I.P. Activities
Hi Rob,
as far i know If re-baseline the progress its does not impact the cost, its only have to shift remaining progress followed by the cost /resource, Unless there is additional activities to be add or labour rate changes (but not very frequent happened) cause there is contract to be followed.