Updating P3 Programmes

9 replies [Last post]
Mario Patel
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 14 Apr 2004
Posts: 23
Groups: None
When you need to update a P3 programme, Do you update the Master or the sub programmes?

Replies

Mario Patel
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 14 Apr 2004
Posts: 23
Groups: None
Thanks
MK TSE
User offline. Last seen 3 years 42 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
I think there is some mis-understanding.
In P3 programme, on data structure, there are 2 levels, one is master and the other is sub (some user will name it project and sub-project).
To make it simple, you need to review the activities (no matter in project or sub-project).
Mario Patel
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 14 Apr 2004
Posts: 23
Groups: None
When you say review the master,do I have to change anything in there. I thought the master and the Target are the same?
MK TSE
User offline. Last seen 3 years 42 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Yes.
Besides the sub-programmes, those activities in master level need to be review their progress also.
Mario Patel
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 14 Apr 2004
Posts: 23
Groups: None
So all I have to do is put the new dates in the sub progs and schedule to current date?
MK TSE
User offline. Last seen 3 years 42 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Except the hommack, need to review all non-complete activites for progress input.
I would like to name the process "progress input" or "progress update" rather "update"
Mario Patel
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 14 Apr 2004
Posts: 23
Groups: None
The Master has been devided into 3 sub programmes. I need to input new dates into the programmes to check progress or slipage.
MK TSE
User offline. Last seen 3 years 42 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Mario,
Would you mind to explain the meaning of ’update’?
Is it for input the progress or preparing a revision. The approach is different.
Also you have mentioned the term ’master’ and ’sub’ of a P3 programme. P3 data structures need to be considered also.
Rajesh Moolakkandam
User offline. Last seen 7 years 43 weeks ago. Offline
Joined: 5 Jun 2004
Posts: 15
Master program is not updated usually.you have to udate the current shedule only.Master program/base program is with which you are comparing the current progress.