Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Float Path in Group and sort

No replies
Abbas Rajabpour
User offline. Last seen 33 weeks 4 days ago. Offline
Joined: 7 Oct 2022
Posts: 25
Groups: None

Hi

I was watching a video in which it used the following picture for group and sort and also filtered the activities on " in progress" and " Not started" 

What is the benefit of using this?

Is it for seeing the critical activities? If yes, why not just filtering by " critical"?

( Would also appreciate it if you let me know what is the meaning of float path and what is the use of it)

 

8305
screen_shot_2022-12-19_at_4.08.47_pm.png

John Reeves
User offline. Last seen 25 weeks 5 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Note if you want to use the Float Path, at least on ver 16.1 or older you have to go to Tools, Schedule, Options, Advanced, - the check the box that says Calculate Float Paths, then you have to put a number - I do not understand why it asked, so I just put some random number like 300.  When asked to analyze a schedule - Float Paths is the first thing I do.  Schedules are generally by WBS - you can't follow them, the Float path shows you the sequences straight through- most important down (common sense will over-ride some).  
 

John Reeves
User offline. Last seen 25 weeks 5 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Note if you want to use the Float Path, at least on ver 16.1 or older you have to go to Tools, Schedule, Options, Advanced, - the check the box that says Calculate Float Paths, then you have to put a number - I do not understand why it asked, so I just put some random number like 300.  When asked to analyze a schedule - Float Paths is the first thing I do.  Schedules are generally by WBS - you can't follow them, the Float path shows you the sequences straight through- most important down (common sense will over-ride some).  
 

Rodel Marasigan
User offline. Last seen 16 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Right Click on the toolbar and select the Activity Critical Path Toolbar: see below

Activity-Critical-Path

Zoltan Palffy
User offline. Last seen 26 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Rodel where is this tool bar located 

Rodel Marasigan
User offline. Last seen 16 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699

If your schedule had a multiple path, the best way of checking the driving activity is to use the float path. The P6 r21 had a new tool bar that calculate float path or driving predecessor and successor activity called Activity Critical Path tool bar.