Max units per time not matching "Limit" line in recourse usage profile bar chart

No replies
Huss PS
User offline. Last seen 2 years 6 weeks ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None

Hi All,

 

I am using P6 V21.

"Limit" line in "Reosrce usage profile" window it is showing above 50h/d (Max units/time set when adding resource).

Has anyone experience similar issue? What could be the reason? and how to fix it?

 

PS: I tried to upload snapshot but unable to see images or load images on this website. probably becasue it's not https. If i can get help on this as well, that would be great.

Thanks 

Huss PS
User offline. Last seen 2 years 6 weeks ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None

It Worked!!! 

You were correct. 

I deleted both calenders and added again. 

Thanks alot.

Huss PS
User offline. Last seen 2 years 6 weeks ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None

I checked that again. Calender for both activities and resources are same.

see below snapshot.

8277
2.png

david kelly
User offline. Last seen 4 weeks 12 hours ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

So, you think the llimit should be 50, but it is really 63?

 

Sounds like a Resource Calendar issue

Huss PS
User offline. Last seen 2 years 6 weeks ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None

It's showing 63.

Huss PS
User offline. Last seen 2 years 6 weeks ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None

It's showing 63.

david kelly
User offline. Last seen 4 weeks 12 hours ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

Can you double-click on one of the histogram bars, and report back the figures?