Is there a technical name for delay caused by not being able to work as scheduled? for example if something is FS instead of SS?

No replies
John Reeves
User offline. Last seen 1 week 2 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Is there a technical name for delay caused by not being able to work as scheduled? for example if something is FS instead of SS? (for example thought could start steel same time as concrete but had to wait until done.)  "Out of Sequence Delay" or "Logic Error Delay" or "Planning Delay"?

Alex Lyaschenko
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 15 Aug 2011
Posts: 59
Groups: None

If a schedule has SS instead of FS (or any other combination) it is just a schedule quality issue that only could be solved by maturing schedule development process. 

Alex Lyaschenko
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 15 Aug 2011
Posts: 59
Groups: None

If a schedule has SS instead of FS (or any other combination) it is just a schedule quality issue that only could be solved by maturing schedule development process. 

Zoltan Palffy
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

any one of those is sufficent