Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cost

3 replies [Last post]
sai krishna raju
User offline. Last seen 4 years 19 weeks ago. Offline
Joined: 8 Jul 2019
Posts: 7
Groups: None
Why ,at completion cost is different from budgeted total cost . The cost is increased at completion cost from budgeted cost

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

put in the actual then adjust the at completion make it equal the budgted costs 

sai krishna raju
User offline. Last seen 4 years 19 weeks ago. Offline
Joined: 8 Jul 2019
Posts: 7
Groups: None

i Checked it is Clicked even then, At completion Cost Is more than Budgeted Cost

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

go to Projects click on the calculations tab on the rigth under resource assignments

make sure that under 

When updating actual Units or Costs that 

Subtract Actual from At Completion is checked