Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

The F9 is Canceled when i close the project

2 replies [Last post]
Lyna Bellahsene
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 21 Oct 2019
Posts: 4
Groups: None

Hi everyone, 

I have a probleme with a project in P6, the dates ( delta of 1 minute but the date change to the day after )  of about 30 activities (30/1600) changes when i close and re open the project. I think that the problem comes from the excel that we import in order to change the ressources. So when i remove the ressources its all ok but, so i try to add the ressources back... same problem

i tried to add another activities with the same sittings it remains the same. 

thanks a lot for ur help!

Replies

Raymund de Laza
User offline. Last seen 31 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762
Check also the calendar used in Resources.
Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

go to edit user preferences and turn your TIMES ON

when you calculate the schedule make sure to set the DATA DATE TIME to 8:00 am or the earliest times on all of your calendar being used.