Printing Gantt Chart

1 reply [Last post]
Ron Beechey
User offline. Last seen 1 year 18 weeks ago. Offline
Joined: 13 Jun 2002
Posts: 61

In print Preview on the 11X17 layout, I can see the data but no bars.   Am I missing something?  I have made a few adjustments but have not found the fix to have the bars show.  This is fresh out of the box P6.  Only started working with this version on a stand-alone.  

 

Looks like I found the problem and it is printing now with the Gantt chart 

 

Thanks for anyone that was thinking about the problem :>)

Replies

Alexandre Faulx-B...
User offline. Last seen 4 days 16 hours ago. Offline
Joined: 20 Jan 2003
Posts: 1308

Hi Ron,

in the preview setup dialog, go to Options,

check that Gantt chart is checked

then, fix the Timescale Start and Finish dates, presumably to Project Start and Project Finish

have a good day,

Alexandre