Schedule% complete & Performance % complete is not appearing

3 replies [Last post]
adab azeez
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50
Greetings to all. I am updating a project in primavera.I need to present schedule % and performance % in the WBS of activities. But it is always showing zero, though the activity sch.% and performance% are rolling up with the update. Need a guidance. Thanks in advance.

Replies

Zoltan Palffy
User offline. Last seen 11 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

glad I could help 

adab azeez
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50
Thank you Mr. Zoltan. If resource unit per price is not zero then % progress will roll up with every status update. I have done it.
Zoltan Palffy
User offline. Last seen 11 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

create an activity for that particular wbs and give it the activity TYPE of wbs summary then it will roll up and summarize that particular wbs for you. You can not roll up the wbs in the way that you are doing it becasue activities can use different wats to mecasure their progress you can use duration % complete, physical % complete or units % complete. So if you tried to summarize them by youe would be mixing applles and oranges and bananas. The soultion is to use WBS summary.