Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Milestone Points on Gantt Chart

1 reply [Last post]
Adam Collins
User offline. Last seen 8 years 18 weeks ago. Offline
Joined: 24 Jan 2012
Posts: 3
Groups: None

Hello 

I am wanting to set marker points/milestones along the activity line for procurement wysiwyg_imageupload::for a high level tender schedule in P6. I have done this before some time ago using dates in the user defined fields to capture the dates (ie: Bid Submission / PO Award / Delivery). 

Has anyone else done this before and can offer some assistance? 

 

Thanks

Replies

Zoltan Palffy
User offline. Last seen 4 days 4 min ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

why not create a unique code for the activities that you want to show then assign the code value to each of theses activities then filter for that code