S Curve & Manpower Histogram

1 reply [Last post]
Asif Mahamood
User offline. Last seen 8 years 31 weeks ago. Offline
Joined: 5 Jan 2014
Posts: 3
Groups: None

Hii

It will be grateful if you could answer these
1- How will you prepare Manpower Histogram for Multimillion Projects?
Do you have any standard formats for determining manpower productivity (eg: slab form work= 6 sq.m /day/ carpenter- My company standard).

Pls send me any templates for preparing manpower histograms.

2- How will you prepare S Curve in Primavera ? or is there any tools available to prepare Planned % vs. Actual % Complete in Primavera.?

Hope to see your reply soon.

Email: asif2q@gmail.com
Mob: +96891198301

Replies

Chris Rymer
User offline. Last seen 2 years 30 weeks ago. Offline
Joined: 11 Jun 2010
Posts: 32
Groups: None
Hi Asif To prepare your S curve, have a look at Project Tracker. It can create your curve straight from P6 without the need to allocate cost or resource. You can download a free trial and see what it can do for you at www.willmer.co.uk or email me at chris.rymer@willmer.co.uk for more information