Bucket planning

2 replies [Last post]
Bichu C C
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 28 Jan 2013
Posts: 3
Groups: None

Dearss..

How to enable bucket planning in p6 to enable to enter budgeted units manually.

Replies

V Kutty
User offline. Last seen 5 years 29 weeks ago. Offline
Joined: 17 Jan 2011
Posts: 23
Groups: None

HI,

Is there a means of stopping P6 from re allocating resources based on the total resources if the activity is delayed.

Thanks,

Abilash Palakkada...
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47

just go to resource usage spread sheet and selct the activity, then u will be able to do bucket planning