Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Fri, 2025-05-23 15:57 Permalink activites that have exteranl activites that have exteranl relationships will have an asterick in the start date column Option 1 go to tools schedule select options then select ignore relationships to and from other projects option #2 filter for all activities right click columns expand the dates availability on the left and choose External Early Start and also choose External Early Finish now in the External Early Start column Blank out the dated now do a fill down a Now do the same thing for the External Early Finish Column Option #3 go to tools global change New (on the right) Where (leave this line blank) then External Early Start = (leave the rest of the line blank) and External Early Finish = (leave the rest of the line blank) then on the right select change then commit changes what ever option that you choose make sure to run the schedule calculations after you run your option Member for 13 years 4 months Member for 13 years 4 months Submitted by rodneyoz on Wed, 2024-05-15 10:00 Permalink Thanks Santosh & Rodel, both Thanks Santosh & Rodel, both suggestions very worthwhile. Rod Member for 20 years 6 months Member for 20 years 6 months Submitted by Santosh Bhat on Wed, 2024-05-08 01:30 Permalink Rodney, take a look Rodney, take a look here: Listing P6 Inter-Project Relationships | Australasian Project Planning (austprojplan.com.au) Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Fri, 2024-05-03 05:34 Permalink The easiest way is to export The easiest way is to export the Activity Relationship to Excel. Make sure to include the 'Predecessor Project' and 'Successor Project' columns. You can then filter from these two columns for the external project links to your Project. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Fri, 2025-05-23 15:57 Permalink activites that have exteranl activites that have exteranl relationships will have an asterick in the start date column Option 1 go to tools schedule select options then select ignore relationships to and from other projects option #2 filter for all activities right click columns expand the dates availability on the left and choose External Early Start and also choose External Early Finish now in the External Early Start column Blank out the dated now do a fill down a Now do the same thing for the External Early Finish Column Option #3 go to tools global change New (on the right) Where (leave this line blank) then External Early Start = (leave the rest of the line blank) and External Early Finish = (leave the rest of the line blank) then on the right select change then commit changes what ever option that you choose make sure to run the schedule calculations after you run your option
Member for 13 years 4 months Member for 13 years 4 months Submitted by rodneyoz on Wed, 2024-05-15 10:00 Permalink Thanks Santosh & Rodel, both Thanks Santosh & Rodel, both suggestions very worthwhile. Rod
Member for 20 years 6 months Member for 20 years 6 months Submitted by Santosh Bhat on Wed, 2024-05-08 01:30 Permalink Rodney, take a look Rodney, take a look here: Listing P6 Inter-Project Relationships | Australasian Project Planning (austprojplan.com.au)
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Fri, 2024-05-03 05:34 Permalink The easiest way is to export The easiest way is to export the Activity Relationship to Excel. Make sure to include the 'Predecessor Project' and 'Successor Project' columns. You can then filter from these two columns for the external project links to your Project.
Member for
16 years 3 monthsactivites that have exteranl
activites that have exteranl relationships will have an asterick in the start date column
Option 1 go to tools schedule
select options
then select ignore relationships to and from other projects
option #2
filter for all activities
right click columns
expand the dates availability on the left and choose
External Early Start and also choose External Early Finish
now in the External Early Start column Blank out the dated
now do a fill down a
Now do the same thing for the External Early Finish Column
Option #3
go to tools
global change
New (on the right)
Where (leave this line blank)
then
External Early Start = (leave the rest of the line blank)
and
External Early Finish = (leave the rest of the line blank)
then on the right select change
then commit changes
what ever option that you choose make sure to run the schedule calculations after you run your option
Member for
13 years 4 monthsThanks Santosh & Rodel, both
Thanks Santosh & Rodel, both suggestions very worthwhile.
Rod
Member for
20 years 6 monthsRodney, take a look
Rodney, take a look here: Listing P6 Inter-Project Relationships | Australasian Project Planning (austprojplan.com.au)
Member for
19 yearsThe easiest way is to export
The easiest way is to export the Activity Relationship to Excel. Make sure to include the 'Predecessor Project' and 'Successor Project' columns. You can then filter from these two columns for the external project links to your Project.