Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Creating WBS in MSP

1 reply [Last post]
Alok Mishta
User offline. Last seen 7 years 8 weeks ago. Offline
Joined: 5 Feb 2017
Posts: 3
Groups: None

Can anybody help me in creating WBS for it.

1.que

plumbing, common results for plumbing, schedule of piping, meter and gauges, schedule for piping and pumps, schedule for fixtures, domestic water piping, booster pumps, water distribution, general duty valves, plumbing piping schedule, schedule for equipment, domestic water pumps, HVAC, central cooling equipment, schedules for HVAC, common work results for HVAC, testing, adjusting and balancing, refrigerant compressor, packaged compressor, refrigerant condenser, packaged water chillers 

2.que

fire suspension, common work results for f.s., schedule for f.s., schedule for fire extinguisher, FS equipment, wet pipe, dry pipe, water spray fixed, sprinkler, system, foam system, schedule for water based system

Replies

Alok Mishta
User offline. Last seen 7 years 8 weeks ago. Offline
Joined: 5 Feb 2017
Posts: 3
Groups: None

in the 2nd que, instead of fire suspension, fire suppression will be there.