Microsoft Project 2013 and Start No Earlier Than Constraints

1 reply [Last post]
Emily Foster
User offline. Last seen 1 year 47 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

Here's a step-by-step guide on how to use Start No Earlier Than Constraints in Microsoft Project 2013 http://ow.ly/TzWf7

Replies

Rafael Davila
User offline. Last seen 16 hours 55 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Do you have vested interests with Planning Planet?

Most of your postings are links to your own site, getting publicity for free.  I do not oppose making your postings in response to discussions generated by others, that should be allowed, but creating your own discussion in order to get free publicity I believe is against Planning Planet Rules.  In any case there must be other places within Planning Planet for those who want to advertise.

At the beginning it was tolerable to me, but not anymore, too much of it!