Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

MSP 2012

No replies
steve soulsby
User offline. Last seen 12 years 13 weeks ago. Offline
Joined: 24 Jan 2012
Posts: 4
Groups: None

Hi all,

i have a couple quick questions.

ill explain what im after then maybe you could point me in the right direction as to where i am going wrong.........

basically i have a programme set up with fixed costs, resource costs and timescales - everything you would expect. when i come to update my project with actuals i would like to keep the  actual activity durations and incurred costs as something completely different.

i want to simply have the activitys and the associated costs as programmed totally seperate to stop it messing up my actuals? does this make sense?

for example - i have site supervision as an activity with 100 man hours spread over three resources. when i update the projects status percent complete to say 50%. 50 man hours has been automatically calculated? - with disregard to what they have actually done - for which i want to input seperately, i want to be able to progress the activity but without the incured cost of hours associated.

i think i have missed a fundamental  here when i have set up each of the activities with regards to how i am wanting to record my costs........

hope im making sense

thanks

 

steve