Cost Control MS Project 2007

2 replies [Last post]
Maarten van Wyk
User offline. Last seen 14 years 13 weeks ago. Offline
Joined: 9 Sep 2010
Posts: 7
Groups: None

Hi there,

 

I loaded the estimate into my project plan in MSP 2007 as cost and material resources. When is a cost resource used?

When I enter % complete, it also calculate my actual cost. I did untick this option but it keeps on doing it. How do I enter my actual costs for each month into the program? How do I get the program not to calculate my actual costs from the % complete, but rather enter it myself on a monthly basis.

 

Regards,

Maarten

Replies

Marcus Possi
User offline. Last seen 34 weeks 1 day ago. Offline
Joined: 27 Feb 2010
Posts: 76
Maarten, It may look strange, but the cost type resource is not working properly not only in 2007 but also in 2010. It is distorting the EVM calculation and you can't use it anymore. The only way is to keep a separated resource in material type, like in the old times of MS 2003. I said it would seem strange, but in fact it is really a misconception of theory and a big unsolved bug. best regards, Marcus Possi
Ellen Lehnert, Mi...
User offline. Last seen 7 years 19 weeks ago. Offline
Joined: 12 Feb 2011
Posts: 20
Groups: None

Cost resources are not updated by the tracking % complete buttons and must be entered manually.  The option to stop the updating of the materials costs is controlled by Tools --> Options --> Calculation --> Updating task status updates resource status.  If you turn that off, you will separate the update to the material resource values.  However, you will also not be updating work completed either.

I hope this helps.

Ellen Lehnert

www.lehnertcs.com - free tips and trick articles