OBS & MSP

2 replies [Last post]
Mohammad Hamed Ga...
User offline. Last seen 2 years 37 weeks ago. Offline
Joined: 18 Dec 2007
Posts: 6
Groups: None
Happy New Year
I wish you all the best in 2008

I know how to organize OBS (Organizational Breakdown Structure) with Primavera but not know how to do it with MSP. If there is the possibility to do it with MSP please let me know.

With best regards,

Replies

Mohammad Hamed Ga...
User offline. Last seen 2 years 37 weeks ago. Offline
Joined: 18 Dec 2007
Posts: 6
Groups: None
Hello Niek,

Thank you very much for your worthful information.

Best regards,

Hamed
Niek Zonneveld
User offline. Last seen 46 weeks 21 hours ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
Hello Hamed,

MSP doesn’t know the clear distinction between WBS and activities as Primavera does; this also means the OBS mechanism isn’t available out of the box.

What you can do in MSP is create the OBS in an Outline Code, but you need to guard the consistency between activities, summary tasks and your OBS code. (in other words, you’ll need to make sure that all activities underneath a WBS (i.e. summary task) have the same OBS code)

Hope this explains,

Niek.