Moving Reports to Excel

2 replies [Last post]
Forum Guest
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
I am attempting to move a standard staffing report which includes both resources and schedule into Excel. The report is called "Who Does What When" in Microsoft Project. Any suggestions? I just want the entire report to move, which would allow me to manipulate the numbers in Excel.

Replies

Se de Leon
User offline. Last seen 2 years 37 weeks ago. Offline
Joined: 15 May 2001
Posts: 321
Groups: None
When you're already in the Export Mapping Dialogue Box, click edit. From this edit box you can already manipulate what data would you like to export from MSP to Excel. If you have questions, feel free to email me.
Ali Hamouda
User offline. Last seen 7 years 48 weeks ago. Offline
Joined: 3 Feb 2002
Posts: 109
Groups: None
Since MS-Project is one of the Microsoft program Familis , so: You can Highlight copy and Past the Information in Excel. Best Luck Ali