Hi Nilesh,Your question is really good!What not to do:  Don't get involved in 'helping' the contractor plan its work. If you do you will accept some responsibility.What to do:1. Make sure payments accurately reflect work actually accomplished.2. As far as possible make sure all of the client inputs are delivered in accord with the original program requirements. If these are delivered later than this the contractor can claim 'pacing' if the deliveries actually cause a delay the contractor can claim the delivery was the overriding cause of the delay and seek EOTs with costs.3. Keep really accurate records of everything done on a daily basis. Date stamped photographs help. Signed records are good. Make sure the progress information is shared with the contractor (no surprises).4. Expect lots of claims from the contractor and gear up early. 5. Don't assume the contractors Head Office knows what is going on.  Regular requests to the head office to explain schedule slippages each month (eg, contract issued last month was for 1000cu.m. only achieved was 700cu.m - please explain) will put pressure on the site to perform. Focus these on one or two key metrics only.It may help to get expert advice early (but this tends to be expensive).Some free resources that mey help are avaiable at: <a href="https://mosaicprojects.com.au/PMKI-TPI-080.php">https://mosaicprojects…;
Wow! Indeed, a really good
Wow! Indeed, a really good question!And a really, really good answer from Patrick!Fraternally in project management,Steve the Bajan
Hi Nilesh,Your question is
Hi Nilesh,Your question is really good!What not to do:  Don't get involved in 'helping' the contractor plan its work. If you do you will accept some responsibility.What to do:1. Make sure payments accurately reflect work actually accomplished.2. As far as possible make sure all of the client inputs are delivered in accord with the original program requirements. If these are delivered later than this the contractor can claim 'pacing' if the deliveries actually cause a delay the contractor can claim the delivery was the overriding cause of the delay and seek EOTs with costs.3. Keep really accurate records of everything done on a daily basis. Date stamped photographs help. Signed records are good. Make sure the progress information is shared with the contractor (no surprises).4. Expect lots of claims from the contractor and gear up early. 5. Don't assume the contractors Head Office knows what is going on.  Regular requests to the head office to explain schedule slippages each month (eg, contract issued last month was for 1000cu.m. only achieved was 700cu.m - please explain) will put pressure on the site to perform. Focus these on one or two key metrics only.It may help to get expert advice early (but this tends to be expensive).Some free resources that mey help are avaiable at: <a href="https://mosaicprojects.com.au/PMKI-TPI-080.php">https://mosaicprojects…;