Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Day Works Schedule

1 reply [Last post]
Ameya Kulkarni
User offline. Last seen 15 years 12 weeks ago. Offline
Joined: 16 Feb 2009
Posts: 10
Hi all,

Could anyone throw some light on " Day Work Schedule"?

Why it is included in tender package?

what is the use of Day work Schedule provided by the engineer to the Contractor?

Regards,

Ameya Kulkarni

Replies

Ken Sadler
User offline. Last seen 4 years 31 weeks ago. Offline
Joined: 14 Jul 2008
Posts: 71
Groups: None
Hi Ameya

A daywork schedule is commonly included within a tender package in order to agree as part of the contract the rates for various time-related activities.

Generally, variations to contract would be valued under one of the 4 headings, in this order;

1 BQ rates
2 Rates derived therefrom
3 Fair value agreed
4 Dayworks

Notice that dayworks is relagated to the last option - this is because it can tend to lead to over-valuation of the work, especially when the need to progress the work with any haste is removed (the longer it takes, the more is to be paid!).

Notwithstanding the reluctance of the Employer to pay dayworks, sometimes it is necessary as it is not possible to value the work under any other heading. Whilst the rates should reflect the level of pricing in the original tender, this is often diffcult to establish and inevitably disagreement will arise. So it is better to set out a schedule of daywork rates and agree these as part of the tender.

Regards

Ken