Change in Lump Sum item

2 replies [Last post]
Omer Hassan
User offline. Last seen 15 years 29 weeks ago. Offline
Joined: 6 Jul 2008
Posts: 18
Groups: None
Can Engineer increase or decrease the amount of lump sum item through variation clause. If yes then please quote the clause under FIDIC 4th edition reprinted 1992.

Thanks
Omer

Replies

Omer Hassan
User offline. Last seen 15 years 29 weeks ago. Offline
Joined: 6 Jul 2008
Posts: 18
Groups: None
Thanks Larry, I also think like that.

Regards,
Omer
Larry Rino
User offline. Last seen 47 weeks 2 days ago. Offline
Joined: 25 Oct 2007
Posts: 64
Omer,

Yes, Engineer can increase or decrease the amount of lump sum item through variation clause 51 of FIDIC 4th ED(1992).

The Clause 51 does not give any restriction to whether variation should be priced as LS, UP, Daywork, Cost plus, etc.

I suggest you check other part of your contract, such as special conditions or commercial clarification or price schedule (if any and as long as applicable), for clearer understanding of contract’s rule of pricing a variation.

Good day...