Impact Curves

1 reply [Last post]
Zq qz
User offline. Last seen 13 years 41 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
PLEASE HELP........

1-What is Impact Curve?
2- How to use impact curves to proactively identify cummulative schedule impacts.
3- What are the 5 criteria to develop the shape of impact curves.

Replies

Matthew Edwards
User offline. Last seen 17 years 34 weeks ago. Offline
Joined: 6 Jan 2006
Posts: 21
An impact curve is total cumulative progress planned v actual. This can be for either manpower on-site, cash flow, substructure progress. It does not identify critical path but can be used to demonstrate simultaneus delays either through late issue of construction information etc