Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Taking over of sections or parts

20 replies [Last post]
ashraf alawady
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
Dear, all
I have a road and infrastructure project which was planned in the pogramme to be devided into 10 stages and each stage consists of 3 working areas and each working area have 3KM length.

As per clause 48.2 of the conditon of contract,the engineer shall issue a taking-over certificate for any substantial part of the permanent works which has been both completed and otherwise occupied by the employer.

Based on the above ,the contractor is asking me to hand over officially every and each working area after completing the works for the said area and open the same for the use of normal traffic.

Shall i agree with the contractor’request which is contractually supported but seems to be un-normal practically since i have to issue 33 nos.of partial taking-over certificate and the maintanence certificates will be issed in different dats accordingly.

Please advice me.
THANKS

Replies

ashraf alawady
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
thank you Edderic,

in this particular project it was very wise suggestion to put a milestone dates in the contract for the areas needs to be handed over partially.
Edderic See
User offline. Last seen 15 years 28 weeks ago. Offline
Joined: 20 Jul 2005
Posts: 25
Groups: None
Hi Ashraf,

For issuance of TOC, my company usually incorporates it on the milestone dates set in the contract. Partial taking-over for substantially completed works can be use for DLP.

Regards,

Ed
Andrew Flowerdew
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Going on your last post, 33!!!!
ashraf alawady
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
If the 33 sections are to be handed over in sections ,what are the logical sections have to be ready and completed to hand over and how many taking over cetificates can be issued for one project.
ashraf alawady
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
The client has directed the engineer to agree with the contractor to certain proceedures and areas which can be logically accepted to make partially taking over.
David Barker
User offline. Last seen 7 years 14 weeks ago. Offline
Joined: 4 Sep 2007
Posts: 27
Groups: None
In Handover 5 things usually happen for Contractor:

1/2 Retention is released
LAD liability ceases
Maintenance period commences
Insuring obligations may cease
Warranty periods may begin

As a result Contractors are usually amenable to early handover

Your Client should be appraised of this in order for the Client to understand the decision that they have to take.

Nicolas Igersheim
User offline. Last seen 8 years 29 weeks ago. Offline
Joined: 25 Jun 2007
Posts: 62
hi ashraf,

one important factor in you pb is time, and that you forget to mention!

How many handovers do you foresee per day, per week,
per month?
If the 33 sections are to be completed the same week
for instance, nobody will gain anything by splitting hairs!

On the contrary if the handovers are to be spread over
a year, no doubt you should come up with a form and a routine for separate handovers!
I could imagine a weekly meeting during which the areas
completed that week would be checked, sealed, signed and delivered

hth
ashraf alawady
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
In the condition of contract ,it is stated that if any part of the permanent works has been substantially completed and has satisfactory passed any tests on completion prescribed by the contract, the engineer may after due consultation with the employer issue a taking-over cetificate in respect to that part of the permanent works before completion of the whole of the works in condition that the contractor shall undertake to complete with due expedition any outstanding works during the defects liability period for that part.
ashraf alawady
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
Can i get more opinion/advises from the others , please
Ronald Winter
User offline. Last seen 4 years 19 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
To begin with, you need to obtain a ‘Relief from Maintenance’ for every section turned-over. Without this, any damage done will still be your responsibility to repair.

Next, you need to ensure unrestricted access to the remaining work sites. You also need to establish noise level and hours guidelines. You need dust and debris guidelines. You need power interruption guidelines.

Finally, You need to establish access boundaries so that no one not in your employ will access any part of the active work area (including your entrance and access areas.) Your insurance and bounding companies need to sign off on this agreement. Without this, you will find that you have voided your contracts and coverage.

Good Luck!
ashraf alawady
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
Did any body has share in arranging partial taking over for a project in stages and what were the guid lines and prenciples.
Clive Randall
User offline. Last seen 17 years 32 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
Dear Ashraf
Going back a little in this thread you advised that the contractor wants to hand over 32 sections.
It would appear however that if no other handover schedule exists within the body of the contract or a handover schedule was not proposed by the contractor at the time of tender it is possible for you to define them now. While you advise that the post tender TQs are part of the contract it may be worthwhile double checking that they are in fact part of the contract.
I would still advise a preliminary discussion is worthwhile with those on your side involved in the award process and indeed a discussion with the client to see what his needs are. You may involve yourself in considerable work, however this may be beneficial to the client if he can get possesion of sections earlier. Overall your efforts may position your bussiness in a favourable position with your client.
In many ways this is about trying to satisfy everybody even if this involves copnsiderable effort on your part.
Just a thought
Clive
Andrew Flowerdew
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Ashraf,

If the sections haven’t been previously agreed then it would appear by the wording you stated that it up to you to agree them now. This may ease your problem, assuming the contractor plays ball and agrees to fewer sections.

No doubt he will be keen to handover the sections as soon as possible for the reasons indicated in my previous post.

How does the contract define sectional completion (if it does)? eg, taken into use by the Employer or similar. Something along these lines may help you divide the project into larger sections if 2 or 3 areas will not be used until all complete.


ashraf alawady
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
Dears,
I was deeply investigating all the contract’sdocuments to find any more details and i got in the tender query and response the following-
"Partial havdover will be accepted by the client with sections to be agreed on site with the engineer."

Did the above give me any strong contractual support during my discussion and negotiation with the contractor for how to devid the project in to reasonable stages for handing over.
Andrew Flowerdew
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Clive,

Totally agree. The sectional completion is probably more relevant to the Employer as it would have been the Employer for his own reasons, came up with the sectional completion requirements of the contract.
Clive Randall
User offline. Last seen 17 years 32 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
I agree with Andrew
Allthough the contract requires you and your colleagues to carry out a considerable amount of work it appears that this was the envisaged sequence of works to enable your client to gain early access to completed sections of the project. Often this is driven by promises to residents that has little to do with the workload it places on the contractor and consultants. Having the contractor sign up to this handover proceedure at the time of award of contract presumes that his rational behind completion takes full account of thse early handovers. You can try and negotiate an easier path to handover but before you approach the contractor I would sound out your client, there may well be a reason why he wants this proceedure adopted. If not then see what the contractor says.
Clive
Andrew Flowerdew
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Ashraf,

You can try and agree whatever you like with the contractor but as each section will pass from his insurance to yours and the issue of the partial completion certificate will possibly start the defects correction period running, I doubt (or would be very unwise to) the contractor will agree.

The contract states the deal that was made, now it’s up to you to carry that deal out.
ashraf alawady
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
Dear, Clive
I need your opinion in the practicality of this process to issue 33 nos.of partial taking over certificates for one project and i said that itis contractually supported but i would like to draw your attention regarding the following:-
*To issue a paital taking over certifucate i have to do te following:-
1- Do my own inspection for the completed areas.
2- Be sure that all qualiyy tests have been done and tests results are in compliance with the contract requirements.
3- Be sure that a suitable corrective actions have been taken for any failed tests .
4- Be sure that no any major works are remaining or avoid the client form using the completed portons safely.
5- write my report and recommendations to the client.

*I have to call the client officially for handing over inspection for any completed portions.

*If the client accept my recommendation, I have to specify the handing over commitee which should include Client’srpresentative,Engineer’srpresentative and contractor’srpresentative .

*The handing over commitee shall inspect the areas to confirm wither those areas have been comlpleted to the satisfaction of the client or not.

*If the areas were ready, completed and accepted, the engineer has to issue a partial taking over certificate for those particular areas.

So is it practical to do all the above said proceedures for each completed area or we can agree with the contractor to devide the project to 5 satges (as example)for handing over so, we can reduce the nos. of partial taking over certificates and reduce the complecated process of releasing the retention amount,issuing maitanence certificates and other contractual proceedures
Karim Mounir
User offline. Last seen 10 years 50 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
u have to issue him a TOC as per clause 48.2 attahced with a punch list.
Clive Randall
User offline. Last seen 17 years 32 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
Ashraf
It appears you have answered your own question

"As per clause 48.2 of the conditon of contract,the engineer shall issue a taking-over certificate for any substantial part of the permanent works which has been both completed and otherwise occupied by the employer."

However check when the maintenance period starts for each section and subsection, you may find even if you have taken over the area maintenance starts only when all areas are completed. This means that for earlier sections the maintenance period is considerably longer than for later sections.
On this basis your taking over certification must explicitly define future responsibilities under the contract.
Kind regards
Clive