Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Certification of NSC work

2 replies [Last post]
Albert kok
User offline. Last seen 19 years 5 weeks ago. Offline
Joined: 25 May 2006
Posts: 3
Groups: None
Hi Guys,

Any idea the certification of work done for NSC work fall under who ??

a) Client side ( appointed consultant )

b) Main contractor side

Replies

Dimitrios Athanas...
User offline. Last seen 18 years 46 weeks ago. Offline
Joined: 8 Jul 2006
Posts: 5
Groups: None
In response to your discussion of certification of payment for NSC a couple of things to add:

The process of how this is done, is by way of application of the Main Contractor to the Engineer for an Interim or Final Certificate sub-suming the Nom Sub-contractor’s claims for payment. This will in most cases be supported by the Main Contractor’s records. Subsequently, the Engineer issues the Payment Certificate ascertaining the amounts due.

Note that still if the Sub-contractor is dissatisfied with the Engineer’s decision, he cannot directly sue or claim against the Employer in arbitration, unless there is a mechanism provided by its contract e.g. name borrowing arbitrations. Any complaints by the NSC must be made through the Main Contractor.

Also, I am puzzled why the UK JCT Form has in its 2005 Forms abolished the NSC Forms altogether. Eager to discuss your views...
Vic Sto. Domingo
User offline. Last seen 14 years 4 weeks ago. Offline
Joined: 1 Jul 2006
Posts: 5
Groups: None
Hi Albert,

Clause 59.5 of FIDIC 1987 provides that: “Before issuing, under Clause 60, any certificate, which includes any payment in respect of work done or goods, materials, Plant or services supplied by any nominated Subcontractor, the Engineer shall be entitled to….”

Clause 5.3 of FIDIC 1999 provides that: “The Contractor shall pay to the Nominated Subcontractor the amounts which the Engineer certifies to be due in accordance with the subcontract.”

Based on such provisions, I believe that the Engineer (Client’s side) is responsible in issuing the payment certificates for works executed by Nominated Subcontractors.