Engineer - Senior Planning, saudi Bin Ladin Group, Makkah Ring Road
|
From January 2013 till now
1- Employer: SBG (Saudi Benladen Group) …..(KSA)
Job description:Planning Engineer,
Project :" Makkah First Ring Road(WAQF Station) "
Responsibilities:
As a Planning & Scheduling Engineer
· Creating project Time Schedule to achieve certain end date
· Checking and Updating project time schedule (using P6 interprise)
· Checking site progress for Weekly update report
Weekly S-curve update
Weekly Manpower update
· Rescheduling main target project to achieve certain end date (by dissolving and extracting activities)
· Preparing baseline GEPCC (General / Engineering / Procurement / Construction / Commissioning) schedule
· WBS, sequence of work, manpower, equipment, all resource
From August 2008 to December 2012
2- Employer: SBG (Saudi Benladen Group) …..(KSA)
Job description:
Planning & Scheduling Engineer,
Material Engineer
Finishing Engineer
Project :" King Abdullah University of Science and Technology "
Projects participated in: Thuwal,80 kilometers (50 miles) north of Jeddah.
Total Area span :more than 362580 m2
Project main web site:www.kaust.edu.sa
Owner representive:Saudi Aramco
Contractor:SBG(Saudi Binladen Group)
Saudi Oger LTD.
Project manegment company:Turner Saudi Arabia
Architect & Lead Designer:Hellmuth,obata+Kassa baum,lp(HOK)
Contracting Capital: 10 milyar saudi reyal
Project consists of
· PH1 73residential buildings (distributed among 7 zones) &
08non-residential buildings (civic buildings)
1.Bank
2.Public Library
3.Galleria
4.Goods Transfer Building
5.Waste Transfer Building
6.Theater
7.Yachet club
8.Marine Oceanic Research Center (MORC)
· PH2 1600 residential villas ( 1 bed ,2 bed ,3bed ,&4bedroom)
· PH3 Coast Guard (HeadQuarters)
National Guard (Soliders Residence , Officer Residence , Mussallah)
Responsibilities:
As a Planning & Scheduling Engineer
· Checking and Updating project time schedule (using P6 interprise) for Phase 1 buildings
· Checking site progress for Weekly update report
Weekly S-curve update
Weekly Manpower update
· Rescheduling main target project to achieve certain end date (by dissolving and extracting activities)
· Ability to prepare baseline GEPCC (General / Engineering / Procurement / Construction / Commissioning) schedule
· WBS, sequence of work, manpower, equipment, all resource
As a material Engineer
· Quantity survey for full items of Phase 3 buildings..(excavation, sand backfilling, pc & rc , finishing,…)
· Tracking the materials from site and stores through revising actual contracts and purchase orders
· Preparing purchase order for material shown to be missing
· Reviewing the material request to help in material tracking
· Modifying shop drawing for subcontractor using AutoCad
· Working on SAES (Saudi Aramco Engineering standard)
As a finishing Engineer
· Part of the MCC team (Mechanical Commissioning Certificate)
· Part of the HOD team (Handing Over Department)
· Closing EIL items (Exception Item List)
KAUST is being registered with the USGBC for LEED certification and is considered a Green Building
From January 2006 to Augest 2008
3- Employer: DCG (design construction group) ….(Egypt)
Job description:
Project Engineer
Planning Engineer,
Procurement Engineer,
Quantity Survey Engineer,
Quality Control Engineer
Projects :-
1. Multi Storage Gamaloons for one the biggest loading and exporting companies (SESCOTRANS) all over Alexandria,Domyat and Suez
2. 4 residential Villas in Mirrage city resort at Katameya(4000 m2)
Responsabilities
· Prepairng the pep (project execution plan) which provides an overall plan for the implementation and execution of the work through completion of the project
· Design simple sections required for site issues
· checking all civil work and construction
· checking all civil drawing and site shopdrawings
· Following up project time schedule using P3 (Primavera Project Planning)
· Checking site progress for weekly update report
weekly S-curve update
weekly Manpower update
· Modifying shop drawing using AutoCad
· Working with coordination between contractor, design consultant and client
· Calculating and listing the material needed for site issues and purchasing them from local market and suppliers
· QC on readymix concrete
· Achieving conrete lab tests for pressure resistance
From January 2003 to January 2006
4- Employer: ACE (Arab consultant Engineers)…. (Egypt)
Job description:
Survey Engineer ,
QC/QA (Quality Control/assurance)
AtOne of the biggest Industrial projects at Middle East
( Abu Zaabal Steel Rolling Factory )
"The project is built on 50 Feddans (750x280m), its space has been expanded to 260 Feddans in Abu Zaabal area, left side from Cairo-Belbis desert road, Kilo34.
The project consists of :
· Main building,
· Services buildings such as:
i. Control rooms,
ii. Electricity plant,
iii. Water tanks,
iv. Water purification plant .
· Administrative building,
· Maintenance workshops,
· Stores,
· Laboratory,...etc.
The project entries had been connected through asphalat & concrete access roads & a whole wall.
The project objective is: rolling & producing of steel iron: cold & hot.
The contract valueis 316 million L.E. (max.)
Project period: 41 months (max.)"
Contractor:Arab Contractors (AC) (Usman Ahmed Usman)
Technical Companies :SMS Group
(SMS SIEMAG, Siemens, LOI, Fulguara, and Herquline Companies )
Consultant : Arab consultant engineers ( ACE ) ( Muhharm Bakhoom )
Contracting Capital:-187,051,678 LE divided to
· AC 122,338,094 LE (arab contractor)
· DSD 64,713,584 LE (ferrometalico)
Responsibilities: Checking all civil and survey work in site ….
· Industrial project
· Heavy Machine Foundation including embedded parts.
· Steel structure foundation
· Water tanks slipform & heavy lifting ( Lift slab Misr )
· High water tank which provides 60 psi (pound per square inch ) at the base of the tank with 42 m high
· Pile Works
1. End bearing piles
2. Displacement piles
3. Replacement piles : the hole is done by a drill and filled with in-situ concrete
4. Sheet piles which are used in deep excavation
· Office building
· Fence &VIP gate
Including:
· Following up project time schedule
· QC on ready concrete mix
· Rechecking shopdrawings
· Calculating and reviewing quantity survey
- Company:
- Industry:
- Job Role:
- Project:
- Region: