Foster Wheeler Energy UK Senior Project Planner

START Date: 
April, 2009
Senior Planning Engineer working within the Offsite & Utilities Team for the Detail Design of IOCL Paradip Refinery. Having developed the Level 2 schedules within Milestones and expanded them to form the Level 3 schedules on Primavera P6 These were updated monthly to determine the status of the project. Overall progress was calculated through the Drawing & Document Control Package.
I then developed the Level 3 Construction Schedule for the Offsites & Utilities which was passed to the Indian Office for further detailing.