Foster Wheeler Energy UK Senior Planner

START Date: 
January, 2007
END Date: 
April, 2008
Senior Planning Engineer assisting in setting up and monitoring the Front End Engineering for a major refinery in NW India for IOCL. The FEL started in Dec 06 and was completed in March 2008. I was responsible for assisting in setting up the Level 3 Schedule using Primavera P5 & monitoring the Progress of the project. Milestones & DMS were also used to monitor progress of the documentation.      