STG International GmbH Planning Engineer

START Date: 
April, 2005
END Date: 
February, 2006
Planning/Scheduling Engineer
STG International GmbH (based in Bargteheide, Germany for Oil & Gas Industry)
In Consortium with JSC Stroytransgaz (Russian Oil & Gas Construction Co.)
Project Location: Khartoum, Sudan, Africa
April 2005-February 2006
     
Involved in Consortium Project Management of 370 Kilometer Melut Basin Oil Development Project, Republic of Sudan for Engineering, Procurement, Construction & Commissioning (EPCC) of Export Pipeline. Submits Planning & Scheduling requirements to the client which include Weekly & Monthly Progress Reports, Recovery Plan, Progress Charts, Resources Table/List & Monthly Invoice. Attends Weekly Meeting with client & consultants.

Appointed for the position as Engineering Coordinator for STG International with client’s approval. Follow-up the status of Engineering submittals with consultants. Disseminate to head office in Germany & sub-contractors the requirements of submittals like drawings, procedures, method statements, etc. Coordinates with MEG Worley - Calgary, Canada (Engineering Design Sub-Contractor) for the design comments. Attends & conducts interface meeting with other Contractors to discuss the work sequence along similar job locations. Coordinate with the Procurement Department on material requirement in line with the design drawings & specifications. Involved in the submission & preparation of Final Documentations. Facilitate the acceptance of Punchlist items.

Company Clients:
Petrodar Operating Company Ltd. (PDOC), Project Consultant: OGP Technical Services Sdn. Bhd. (subsidiary of Petronas)