Al Harbi for Trading & Contracting Ltd. Planner

START Date: 
March, 2007
Infrastructure in ZONE A, JUBAIL 2( 136-CO1 & 072-C31R Project)
SEA WATER COOLING System,
Cost SR 157,727,738.74 / SR 441,323,478.13

Nature of Work :

•     Prepares Bar Chart & CPM in Primavera Version 3.2 or higher version.

•     Prepares Bi-Weekly Accomplishment Progress Project Status Report submit to Royal Commission Head Office Jubail.

•     Responsible for the preparation of Monthly Report submit to Royal Commission Head Office Jubail.

•     Liase with the Royal Commission (Client) appointed representative on all report in Primavera Version 3.2 or higher version.

•     Monitoring of weekly progress accomplishment in site for updating in Primavera P3 percent (%) completed.

•     Take photo for weekly monitoring report to be submit to Royal Commission Head Office Jubail.

•     Study and familiarized construction drawings and specs for civil, structural electrical and mechanical works.

•     Submit Bi-weekly report & delayed/critical activities to Project Manager for evaluation.

•     Coordination with the Planning & Cost Manager/Project Manager at site related to delays of the project.

•     Prepares & estimates quantity of pipes needed in site for preparation for installation.

•     Prepares & estimates of Cathodic Protection for Headworks South / North &
Pumpstation Area.

•     Prepares schedule for Headworks (Energinazation) & Pumpstation in Primavera P3 version 3.2.