The Linde Group / Linde KCA Dresden GmBH Senior Planner

START Date: 
February, 1999
END Date: 
August, 1999
CRACKER REVAMP
Responsible for the on-site planning and scheduling of various scopes of work for a six week shutdown for the Cracker Revamp. The scopes consisted of the removal and reinstallation of furnaces, pipework, equipment, steelwork, foundations, electrical and instrumentation. Produced management graphics and progress reports.