TECHNIP Planner
START Date:
May, 2007
END Date:
November, 2008 • To provide project schedule as per the requirement on TOR for proposal submission
• To develop detailed project plan and schedule
• To provide progress measurement and report on weekly basis
• To provide updated schedule and two week look ahead on weekly basis
• To provide forecast schedule and delay analysis
• To attend project meeting
• To provide project S-curve and manpower loading schedule
• To provide project report to project manager / project engineer
• To provide time impact analysis due to change order / additional scope
Project Reference and Client:
LKU-E Dehydration Detailed: PTTEP SIAM LIMITED
LKU-F Dehydration Detailed: PTTEP SIAM LIMITED
MOC Cracking Furnace: SCG
Quick Development of Additional Power Generator: PTTEP SIAM LIMITED
Tantawan Expansion FEED Phase: COTL
Benchamas Fire Protection System Upgrade: COTL
Communication tower FEED Phase: COTL
New LPG & Flare Header Project: Thai Oil
S1 Power System Expansion Upgrade Detailed Design: PTTEP SIAM LIMITED
CO2 Reinjection study: PTTEP
Bongkot Phase 4A: PTTEP
BG Hydra Project PK & SWP Wellhead Platforms: CUEL
Satun Produced Water Injection Detailed Design: CTEP
CPOC JDA Block B-17 Field Development: Ramunia
• To develop detailed project plan and schedule
• To provide progress measurement and report on weekly basis
• To provide updated schedule and two week look ahead on weekly basis
• To provide forecast schedule and delay analysis
• To attend project meeting
• To provide project S-curve and manpower loading schedule
• To provide project report to project manager / project engineer
• To provide time impact analysis due to change order / additional scope
Project Reference and Client:
LKU-E Dehydration Detailed: PTTEP SIAM LIMITED
LKU-F Dehydration Detailed: PTTEP SIAM LIMITED
MOC Cracking Furnace: SCG
Quick Development of Additional Power Generator: PTTEP SIAM LIMITED
Tantawan Expansion FEED Phase: COTL
Benchamas Fire Protection System Upgrade: COTL
Communication tower FEED Phase: COTL
New LPG & Flare Header Project: Thai Oil
S1 Power System Expansion Upgrade Detailed Design: PTTEP SIAM LIMITED
CO2 Reinjection study: PTTEP
Bongkot Phase 4A: PTTEP
BG Hydra Project PK & SWP Wellhead Platforms: CUEL
Satun Produced Water Injection Detailed Design: CTEP
CPOC JDA Block B-17 Field Development: Ramunia
- Company:
- Industry:
- Region: