PLANNING ENGINEER, Delta Emirates Contracting Co. LLC, (1)2 Nos. (2B+G+7 Stories + Gymnasium/Swimming Pool Building), (2) 3B+G+14 Stories+ Swimming Pool (Office & Residential) Building, (2) Dubai Rehabilitation and Handicapped Center

START Date: 
September, 2007
END Date: 
April, 2009

Job Responsibilities:

  • Preparation, submission and updating of the Project Baseline Program (using Primavera Project Management P5.0) including;
  • Project detailed construction schedule/program.
  • Project material procurement schedule.
  • Project shop drawings schedule.
  • Project labor histograms.
  • Project Cash Flow.
  • Preparation of Delay Impact and Extension of Time (EOT) Claims Programs (Variation Claims).
  • Recording and reporting the actual progress of the work versus the planned work.
  • Preparation of Weekly/Monthly Progress Reports.
  • Follow up of Submittals, Procurement Schedule, etc.
  • Preparation of In-house program for the construction team to expedite the work.
  • Preparing Daily Site Reports for the consultant and Issuing Daily/Weekly Construction Schedules for the Construction Team.

Projects:
Projects include high-rise buildings up to 14 stories and lateral (horizontal) buildings.

  1. Dubai Rehabilitation and Handicapped Center (Started in June, 2007 and Completed in August, 2008).
  2. 2 Nos. (2B+G+7 Stories + Gymnasium/Swimming Pool Building) in Marina, Dubai.
  3. 3B+G+14 Stories+ Swimming Pool (Office & Residential) Building at Al Barsha First, Dubai.
    1148
    Dubai Rehabilitation and Handicapped Center for DHCC
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Forensic Analysis): 
2500