Consolidated Contractors International Co -Qatar Planner

START Date: 
March, 2003
END Date: 
March, 2004
CCIC – QATAR - RAS LAFFAN ONSHORE EXPANSION PROJECT (LNG PLANT TRAINS)
REPORTING TO: Planning Manager
•     Progress Assessment/Quantity Analysis every week compared with Client’s Targets
     Civil, Building, Struc. Steel, Equipments, Piping prefab/install’n, Elect / Instrument
     Hydro testing, Insulation, Painting as well as fireproofing.
•     Updating Construction Schedule PRIMAVERA P3 version 3.0 (level 4) after rolling up progress from level 7 using Talisman, Pyramid, Excel, Access.
•     Weekly meeting with Client CMS&A along with Discipline Engineers and Site Manager
•     Weekly Report to Head Office Athens depicting Sch/Act Progress discipline wise, sub project wise, area wise with manpower/plant at site synopsis and areas of concern.