CONSTRUCTION MANAGER, Consorcio KCT CUMANA II, EPC - DT 230 kV S/E Guanta II - S/E Casanay - S/E Guiria

START Date: 
March, 2006
END Date: 
October, 2008

Consorcio KCT Cumaná II, Sucre State, Venezuela                                                     Aug 2007 – Oct 2008

http://www.planningplanet.com/taxonomy/term/13452/all?page=5

http://www.cielemca.com.ve/

Consortium formed by Cielemca C.A, Trime C.A. and Constructora KBT

Construction Manager - Transmission Lines

Project:EPC contractto build Two 230 kV Double Circuit Transmission lines for CADAFE consisting of line with 300 km length, 700 auto-supported towers with 6,000 Tons of galvanized steel, Double Circuit 3-phase conductors and two OPGW cables all the way. The value of the project is $50 MM USD started in January 2006, with 1,200,000 man-hours planned

Construction Manager / Resident Engineer                                                               Mar 2006 – Jul 2007

Project:EPC contractto build a 230 kV Double Circuit

Transmission line for CADAFE with line length measuring 150 km, 330 auto-supported towers with 2,600 Tons of galvanized steel, Double Circuit 3-phase conductors and two OPGW cables all the way. Project values to $24 MM initiated in January 2006, with 560,000 man-hours planned

 

  • Accountable for Project Planning, Management, Quality Assurance and Cost Control
  • Designed & implemented Project scheduling, monitored projects and conducted inspections
  • Corresponded with clients, managed escalations & claims and liaised with Labor Unions

Supervised 1000 direct workers and 60 staff personnel as well as 350 direct workers and 20 staff personnel respectively
 