Petrochemical Oil & Gas Rates & Build Times

Hi
Could you please advise where can I find the Petrochemical Oil & Gas Rates & Build Times and man-hour norms.

thanks and regards

ouldk1@hotmail.com
Karim

 

Comments

Estimation of Manhours

Dear Karim, Usually there are standard norms of every company for estimation of manpower. There are standard manhours assigned for every activity on the basis of which we estimate the required manpower against the contractual quantities/quantum of work to be executed. Then we monitor the progress against the same and monitor the efficiency against the same standard manhours.

Estimation of Manhours

Dear Karim, Usually there are standard norms of every company for estimation of manpower. There are standard manhours assigned for every activity on the basis of which we estimate the required manpower against the contractual quantities/quantum of work to be executed. Then we monitor the progress against the same and monitor the efficiency against the same standard manhours.

Estimation of Manhours

Dear Karim, Usually there are standard norms of every company for estimation of manpower. There are standard manhours assigned for every activity on the basis of which we estimate the required manpower against the contractual quantities/quantum of work to be executed. Then we monitor the progress against the same and monitor the efficiency against the same standard manhours.

Estimation of Manhours

Dear Karim, Usually there are standard norms of every company for estimation of manpower. There are standard manhours assigned for every activity on the basis of which we estimate the required manpower against the contractual quantities/quantum of work to be executed. Then we monitor the progress against the same and monitor the efficiency against the same standard manhours.

Estimation of Manhours

Dear Karim, Usually there are standard norms of every company for estimation of manpower. There are standard manhours assigned for every activity on the basis of which we estimate the required manpower against the contractual quantities/quantum of work to be executed. Then we monitor the progress against the same and monitor the efficiency against the same standard manhours.

Estimation of Manhours

Dear Karim, Usually there are standard norms of every company for estimation of manpower. There are standard manhours assigned for every activity on the basis of which we estimate the required manpower against the contractual quantities/quantum of work to be executed. Then we monitor the progress against the same and monitor the efficiency against the same standard manhours.

Estimation of Manhours

Dear Karim, Usually there are standard norms of every company for estimation of manpower. There are standard manhours assigned for every activity on the basis of which we estimate the required manpower against the contractual quantities/quantum of work to be executed. Then we monitor the progress against the same and monitor the efficiency against the same standard manhours.

estimating piping demolition, fabrication and installation

Our eTaskMaker planning tool can assist you with estimating manhours for piping demolition, fabrication and installation.  It actually generates resource loaded field execution schedule fragnets that can be exported to your preferred scheduling software.

PIPELINE COSTING

 I just joined a company in the oil and gas recently and part of my job is to present a cost estimate on pipline and other activities of oil and gas.

Please can anybody furnish me with the details of the best available approach in cost estimation especially in the oil and gas.

Any available template will be appreciated.

You can reach me on my e-mail please ukahsme@yahoo.com

Thank You.

Samuel Ukah.

PIPELINE COSTING

 I just joined a company in the oil and gas recently and part of my job is to present a cost estimate on pipline and other activities of oil and gas.

Please can anybody furnish me with the details of the best available approach in cost estimation especially in the oil and gas.

Any available template will be appreciated.

You can reach me on my e-mail please ukahsme@yahoo.com

Thank You.

Samuel Ukah.

  i am karthik   I would like

 

i am karthik

 

I would like to introdue myself as a fresher in this field. I recently discovered "planningplanet" which is incredibly helping for people like us.
 

Dear karim,

 

 i also same doubt, i was working in refinery project, any body have piping& equipment fabrication norms & manhour,same for erection, pls send this mail id: jk_jayaraman@yahoo.com

otherwise how to calculate the wightage for all activity(overall progress ) for eg

excavation     3975 cum

pcc                300cum

rcc               690 cum

back filling    2800cum

pls could explain above how to assign the weightage, without perunit how to calculate( 1unit excavation-4manhour for eg ) , any body have norms pls send

once again i ask to you dear all, i get suffer without data going to planning

pls send  the data


 

Petrochemical Oil & Gas Rates & Build Times and man-hour norms

Karim - Due to the varied nature of the work in the oil and gas industry and the work locations I believe there are no norms. In my experience each company that has experience has developed their own closely guarded "rates", based on hard earned experience, to which they apply location and complexity factors. Many speak of a "Gulf Coast Standard" which suposedly is based on work done along the US Gulf of Mexico coastal area from Mississippi to Corpus Christi, Texas; it is a myth. Each company has their own Gulf Coat Standard.

manpower histogram

Please I need more illustration on manpower histogram using the P3