Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

United States (NA.US)

Planner

START Date: 
December, 2009
Current Role

CH2M Hill Planner

START Date: 
December, 2009
Current Role

Black & Veatch Ltd Planner

START Date: 
July, 2006
Am actually a Project Controls Analyst and P5/P6 Administrator. Transition and Train Planners from P3 to Primavera Project Management and help kick off major EPC projects. Import all Excel and XER files and maintain databse integrity. Great Compnay!

Planner

START Date: 
December, 2009
Current Role

The Dow Chemical Company Planner

START Date: 
December, 2009
Current Role

International Architects & Designers Planner

START Date: 
December, 2009
Current Role

Planner

START Date: 
December, 2009
Current Role

Skanska USA Building Inc Planner

START Date: 
December, 2009
Current Role

city of jacksonville Planner

START Date: 
November, 2009
Current Role

Project Controls Engineer, Bechtel Corporation, New Jersey Light Rail Project

START Date: 
May, 1999
END Date: 
October, 2000

New Jersey Light Rail Project

Client: New Jersey Transit Corporation
$615 million design, build, operate and maintain a 34-mile diesel light rail transit system extending from Trenton to Camden, N.J.

•Monitored cost reports and provided weekly and monthly cost reports to my Project Manager.
•Coordinated with construction, field engineering teams to establish logical work sequences
•Created (weekly and monthly) cost and schedule tracking charts and reports.