Tai Wai Station

Planning Manager, New World Construction Limited, Tai Wai Station

START Date: 
March, 2016

How to show the Scheduled % of work for a group of activities.

Cannot show under the WBS Group.

Put all activites under the same WBS and add an activites (WBS summary).

Then it can show the scheduled % for the group of activites.

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
1000