Nickel West KNSC 2010 August Major Outage

Shutdown Planner, BHP Billiton, Nickel West KNSC 2010 August Major Outage

START Date: 
June, 2009
END Date: 
September, 2009

 

Three month contract at Kalgoorlie Nickel Smelter for a 12-day major plant shutdown in late August. One of two Planners responsible for developing, monitoring and progressing shutdown schedule consisting of over 6,000 activities.

 

Schedule involved works across all areas of the plant, as well as requirements for running down the plant leading up to the shutdown and running up the plant at the completion of the shutdown – critical to enable production to recommence on time.